A and B working together can finish a piece of work in 8 days while B alone can do it in 24 days. In how many days can A alone finish the work?
Answer: C
P and Q can do a job in 24 days, Q and R can do it in 30 days, while P and R can do it in 40 days. X is four times as efficient as P, Y is half as efficient as Q, and Z is 2.5 times as efficient as R. Determine the number of days required to complete the same job if X, Y and Z work together.
Answer: D
Pipe A can fill a tank in 12 minutes; pipe B can fill it in 18 minutes, while pipe C can empty the full tank in 36 minutes. If all the pipes are opened simultaneously, how much time will it take to fill the empty tank completely?
Answer: C
If Mohit can complete rd of a work in 24 days, then in how many days can th of the work be completed by him?
Answer: B
It takes A and B, 3 and 6 hours, respectively, to complete a certain work. If they work on the alternate hour. How long will it take them to accomplish the task?
Answer: B
A can do a work in 4 days and B in 12 days. If they work on it together for 2 days, then the fraction of the work that will be left is:
Answer: C
Inlet Pipes A and B can together fill an empty tank in 1.5 hours. Outlet Pipe C, when opened alone, can empty the completely filled tank, in 4.5 hours. When only Pipes A and C are opened together, the empty tank is filled in 6 hours. Find the time taken by Pipe B, when opened alone, to fill the empty tank.
Answer: B
Anil and Bipin together can complete a work in 15 days, while Bipin alone can finish it in 20 days. In how many days can Anil alone finish the work?
Answer: B
Susan can type 12 pages in 6 minutes. Mary can type 6 pages in 12 minutes. Working together, how many pages can they type in 32 minutes?
Answer: A
Work done by 8 men is completed in 10 days. The same work can be completed in 12 days when done by 10 women. How many days will it take to complete when 4 men and 4 women are employed to perform the same job?
Answer: A
10 women can do a work in 6 days and 6 men can do the same work in 5 days. If all these men and women work together, then how many days will they take to finish this work?
Answer: A
14 persons can build a house in 60 days. How long will it take 30 persons to build the same house, provided that they all work at the same rate?
Answer: A
12 men can complete a work in 10 days. How many more men are required to complete the work in 6 days?
Answer: C
30 men can complete a work in 12 days. After 6 days, 24 more men joined them. How many days will they now take to complete the remaining work?

Answer: A
A can finish a work in 20 days and B can complete the same work in 15 days. B worked for 9 days and left the job. In how many days can A alone finish the remaining work?
Answer: B
10 men can do a work in 25 days. After 12 days of work, 3 more men were engaged to finish the work. The number of days required to complete the remaining work is:
Answer: A
Amar can complete a work in 15 days, and Prem, in 12 days. Starting with Amar, they work on alternate days. In how many days will the work be completed?

Answer: A
A and B alone can do a piece of work in 4 and 9 days, respectively. In how many days will the work be completed, if they both work on alternate days, starting with B?

Answer: B
Raja and Rocky together can complete painting work In 5 days. Together they both start painting, but after 2 days, Rocky falls sick and leaves the work. If Raja completes the remaining painting in 4 days, find the number of days in which Rocky alone can do the work.
Answer: C
A and B can do a piece of work in 5 days and 10 days, respectively. They began the work together but A left after some days and B finished the remaining work in 8 days. After how many days did A leave?

Answer: D
A and B are equally efficient, and each could individually complete a piece of work in 30 days, if none took any holiday. A and B started working together on this piece of work, but A took a day off after every four days of work, while B took a day off after every five days of work. If the duo had started work on 01 August 2022, on which date was the work completed?
Answer: D
A alone can finish a work in 15 days. A works only for the first two days and last two days. The rest work is done by B and the work is completed in 20 days. In how many days A and B together can finish the work?

Answer: C
A and B can finish a work in 10 days, B and C can finish it in 12 days and C and A can finish in 6 days. In how many days A alone can finish the work?

Answer: C
In a company, a piece of work can be completed in 4, 6 and 18 days alone by R, S and T, respectively. In how many days will the work be completed if they work together? (Rounded off to 2 decimal places)
Answer: B
Suresh and Anil are working on a special project. Suresh takes 5 hours to type 40 pages and Anil needs 6 hours to type 32 pages on a computer. How much time will it take them to type a 110 - page assignment if they work on two different computers?
Answer: A