218 questions asked across 4 exam years, newest first
Pipe A and pipe B running together can fill a cistern in 6 minutes. If B takes 5 minutes more than A to fill it, then the time in which A and B will fill that cistern separately will be, respectively, __________ .
Answer: D
A can complete a piece of work alone in 120 days, while A and B, working together, can complete this piece of work in 72 days. In how many days can B, working alone, complete this piece of work?
Answer: A
Each inlet pipe can fill an empty cistern in 84 hours while each drain pipe can empty the same cistern from a filled condition in 105 hours. When the cistern is empty, 9 inlet pipes and 10 outlet pipes are simultaneously opened. After how many hours will the cistern be completely filled?
Answer: A
A petrol tank is of length 50 m, breadth 25 m, and depth 10 m. How many litres of petrol can be accommodated in the petrol tank when it is completely filled?
Answer: A
10 women take 16 days to complete a work which can be completed by 6 men in 8 days. 12 men started working and after 2 days 6 men left, and 5 women joined them. In how many days will the work be completed?

Answer: D
X, Y और Z एक कार्य को क्रमशः 5 दिन, 15 दिन और 30 दिन में पूरा कर सकते हैं। यदि X को Y और Z द्वारा प्रत्येक दूसरे दिन एक साथ सहायता दी जाए तो कार्य कितने दिनों में पूरा हो सकता है?
Answer: B
Abraham can complete a work in 9 days, while Andrew can complete the same work in 6 days. In how many days can they complete the work if they work together?

Answer: B
A, B और C समान क्रम में बारी-बारी से कार्य करते हुए 15 दिनों में एक कार्य पूरा कर सकते हैं। A की दक्षता B के बराबर है, और C की दक्षता A के बराबर है। यदि वे क्रम C, A और B में बारी-बारी से कार्य करते हैं तो कार्य कितने दिनों में समाप्त हो जाएगा?
Answer: C
15 men complete a work in 10 days. 15 women complete the same work in 12 days. If all these men and women work together, then the number of days required to complete that work is:

Answer: A
रमेश अकेले किसी कार्य को 24 दिनों में पूरा कर सकता है। रमेश और सोमेश इसे 8 दिनों में पूरा कर सकते हैं। सोमेश अकेले कार्य को पूरा करने में कितना समय लेगा?
Answer: D
4 पुरुष और 6 महिलाएँ एक काम को 8 दिनों में पूरा कर सकते हैं, जबकि 3 पुरुष और 7 महिलाएँ इसे 10 दिनों में पूरा कर सकते हैं। 25 महिलाएँ इसे कितने दिनों में पूरा करेंगी?
Answer: B
पुरुषों के एक समूह ने 13 दिनों में एक कार्य करने का फैसला किया लेकिन प्रत्येक दिन के बाद 9 पुरुष कार्य छोड़ते गए। परिणामतः, कार्य 16 दिनों में पूरा हो पाया। प्रारंभ में समूह में कितने पुरुष थे?
Answer: B
राजू और रजत एक साथ कार्य करते हुए एक कार्य को पूरा करने में 5 दिन का समय लेते हैं। यदि राजू अकेला इस कार्य को 7 दिन में कर सकता है, तो रजत उसी कार्य को कितने दिन में पूरा करेगा?
Answer: D
P and Q together complete a job in days. R and S complete the same job in days. If P, Q, R and S work together, how many days do they need to complete the same job?
Answer: D
A can finish a work in 60 days. He works at it for 15 days and then B alone finishes the remaining work in 48 days. In how much time can A and B working together finish the work?

Answer: A
A can complete of a work in 7 days and B can complete of the same work in 10 days. In how many days can both A and B together complete the work?
Answer: C
The pie chart below shows the distribution of female employees working in a company in five different districts (A, B, C, D and E). Total number of female employees in five districts = 136000 What is the total number of female employees working in a company in district C and district D?

Answer: A
2 पुरुष किसी कार्य को 6 दिनों में पूरा कर सकते हैं और 3 महिलाएं उसी कार्य को 4 दिनों में पूरा कर सकती हैं। तो बताइए कि 1 पुरुष और 2 महिलाएं प्रतिदिन एक साथ मिलकर काम करते हुए उस कार्य को कितने दिनों में पूरा कर लेंगे?
Answer: A
A can complete a piece of work in 14 days, while A and B together can complete it in days. How long will B alone take to complete it?
Answer: D
कॉलेज छात्रों के एक समूह ने एक परियोजना को 10 दिन में पूरा करने का फैसला किया। प्रत्येक दिन 2 छात्र बाहर हो जाने के कारण परियोजना 15 वें दिन के अंत में पूरी हो गई। परियोजना की शुरुआत में छात्रों की संख्या _______ थी।
Answer: A
4 आदमी एक साथ मिलकर किसी कार्य को 18 दिनों में पूरा कर सकते हैं। उसी कार्य को 12 दिनों में पूरा करने के लिए कितने और आदमियों की आवश्यकता होगी?
Answer: C
20 महिलाएं और 15 पुरुष मिलकर एक कार्य को 6 दिनों में पूरा कर सकते हैं। एक अकेली महिला को काम पूरा करने में 150 दिन लगते हैं। एक अकेला पुरुष कितने दिनों में काम पूरा कर सकता है?
Answer: A
A one metre pipe is made with inner diameter equal to outer radius. How much material (in cubic units) is required to make the pipe, if it can hold cubic metres water in it?
Answer: A
P, Q and R can complete a piece of work in 10 days, 15 days and 20 days, respectively. If they work together, in how many days can they finish the same work?

Answer: A
P एक कार्य को पूरा करने में Q से दोगुना या R से तीन गुना अधिक समय लगता है। यदि वे एकसाथ कार्य करें, तो वे कार्य को दो दिन में पूरा कर सकते हैं। Q को अकेले वह कार्य पूरा करने में कितना समय लगेगा?
Answer: B